RSP has recently completed a wide-ranging external installation at prestigious commercial premises in Winchmore Hill, North London. This represented a significant upgrade and enhancement to the property and involved the skilful and imaginative use of quality materials and planting schemes.
Originally RSP was contracted to lay slab and paving but due to the thorough and professional way we handled the job our remit was extended to cover the entire schedule of external works. In consequence, the former plan for an 8-week project was now revised up to foreseeing a 12-week time to completion.
RSP supplied a workforce of between four to ten personnel on site every day, together with a supervisor working closely with the client management team on site. After digging out the existing groundworks, the team put in new tarmac, slab paving and porous paving. New fencing was installed and new turf laid, while an attractive range of plants was bedded in to complete the attractive external environment of the property.